Key Takeaways

  • In Great Britain, a machine bought direct from overseas needs a declaration and CE or UKCA marking before you put it into service.
  • Safety standards differ by region.
  • The electrics on imported machinery need attention more often than not.
  • A cheaper purchase price can mislead, so budget for engineering, testing, translation and documentation after import.
  • Modifying a machine usually doesn’t need new marking, but any significant modification can make you the manufacturer.
  • Verify the paperwork against the machine and don’t accept a mark or declaration at face value.

Machinery may be imported because it’s apparently cheaper or because a parent company mandates it. However the cost of modification and ensuring compliance can mean there’s no real financial saving.

A machine built to another region’s standards may need re-engineering, especially its electrics, before it can lawfully be used here. Its CE or UKCA marking and declaration must be checked, not assumed. This guide covers who is responsible, what to check by country of origin, and how to budget and verify before installation.

Is imported machinery legal to use in the UK?

Yes, if it meets the Supply of Machinery (Safety) Regulations 2008 (SMSR 2008). Before machinery is placed on the market or put into service, the responsible person must carry out a conformity assessment, compile a technical file, draw up a declaration of conformity and apply UKCA or CE marking. A machine without these can’t lawfully be put into service.

Once it is in use, the Provision and Use of Work Equipment Regulations 1998 (PUWER) apply as well. For a newly imported machine, Regulation 6 requires inspection where its safety depends on how it is installed. That means inspection after installation and before first use, and after assembly at a new site.

Who is legally responsible?

Situation Who is responsible
You bought it from a UK supplier The duty sits upstream with your supplier, and you owe PUWER duties in use.
You bought it direct from overseas You may be the responsible person, because HSE guidance says whoever first places it on the market or brings it into use takes on the conformity duties.

SMSR 2008 has no separate importer role, so a direct importer takes on the manufacturer’s tasks, including the technical file, declaration and marking.

Do CE and UKCA marking both work, and what changes on 20 January 2027?

CE marking has been recognised in Great Britain since Brexit, and since 1 October 2024 that recognition has been indefinite. UKCA marking is a valid alternative. A mark is only the manufacturer’s claim of conformity, and it doesn’t prove the machine is safe.

From 20 January 2027, Regulation (EU) 2023/1230 replaces Directive 2006/42/EC. In Great Britain, SMSR 2008 continues to govern supply, as amended by SI 2026/867. A responsible person can then use the CE route by meeting the EU Regulation’s requirements, including the technical documentation, EU declaration of conformity, instructions and CE marking. The documentation, declaration and instructions must be in English and the documentation and declaration must be available to enforcement authorities for at least 10 years. CE marking has been recognised in Great Britain indefinitely since 1 October 2024, so UKCA marking is an alternative rather than a requirement.

EU-built machines will arrive with declarations citing the new Regulation, so check that each names the manufacturer, machine and serial number. Machinery placed on the market or put into service from 20 January 2027 must meet the new Regulation to use the CE route rather than the Directive 2006/42/EC. The Government intends to update SMSR 2008 further, so recheck the position before you buy. Refer to our CE and UKCA marking service or contact us for further guidance.

Does modifying a machine mean it needs new CE or UKCA marking?

Usually not, but you still have duties. HSE guidance says that in most cases a modified machine doesn’t need new conformity marking, whether it carries CE or UKCA marking. It must still be safe and meet PUWER. The exception is a substantial modification, which can create a new machine in law. HSE’s example is fitting CNC control to a previously manual machine, which introduces new risks such as automatic programmed operation. As an employer putting this machine into service, you assume the manufacturer’s duties: conformity assessment, technical file, declaration and marking. Record your reasoning for every modification, including when you decide a change is not substantial. Our PUWER services can help you assess it.

Do Northern Ireland's rules differ?

Yes. From 20 January 2027 the EU Machinery Regulation applies directly in Northern Ireland and SMSR 2008 is revoked there. Importers face their own obligations and a UK(NI) indication may be needed, so check Northern Ireland requirements separately.

Why do safety standards differ around the world?

Each region has its own electrical supply, standards and certification schemes, and a machine that is compliant in one country isn’t automatically compliant in Great Britain. European machines are built to harmonised EN standards, including EN 60204-1 for electrics and EN ISO 13849-1 for safety-related controls. US machines are commonly built to NFPA 79 with UL-listed components, on a different supply voltage and a 60Hz frequency. Chinese machines are typically built to China’s national standards, which can differ from the EN versions. Supply, component approvals, wiring practice and documentation can all vary. The machine should be assessed against the rules of the country where it is placed on the market, which for an import into Great Britain means the rules that apply to you, not those of the country of origin.

What to check on US-sourced machinery

US machines often arrive with no CE or UKCA marking and no declaration. If so, the conformity assessment falls to whoever supplies the machine into Great Britain, which may be you if you are importing directly. Compare supply voltage and frequency with the machine’s design, then check the electrics against EN 60204-1, safety control performance against EN ISO 13849-1, and the emergency stops, interlocks and guarding.

Case study: US machines imported to polymer processing plant.

A multinational polymer systems manufacturer was installing machines from its US parent company. Built for a US electrical supply, they lacked compliant emergency stops and guarding. We re-engineered them on site and in our Elland workshop to limit disruption, upgrading components for a 230V/50Hz supply and bringing the electrics into line with EN 60204-1. We also fitted interlocking, emergency stops and guarding, and addressed safety-related control functions to EN ISO 13849-1.

What to check on machinery from China

Chinese machinery can be well made, but a CE mark on the nameplate is not evidence of conformity. Sometimes Chinese exporters use it to signify “China Export”. Ask for the declaration and check that it names the manufacturer and correct model, matches the serial number on the machine rather than a generic template, and lists the standards applied. Ask to see the technical file, and check that both exist in English. Where third-party assessment is required, verify the certificate with the issuing body. Inspect the electrics, guarding and stopping functions closely, because that is where adaptation is most often needed.

How much electrical work does imported machinery need?

In our experience, around nine in ten imported machines need some electrical work, although  this can vary from a few minor changes or a complete re-engineering of the control system. Only an assessment of the machine’s electrics against your site supply and the electrical safety standard EN 60204-1 will indicate if work is needed and how much.

In practice the work tends to fall into three broad levels:

  • Minor changes. The electrics are largely suitable, as is common with EU-built machines or those with dual-rated components. Work might be needed to a supply transformer, an isolator or connection to suit the site, or a few component replacements, English labelling and corrected schematics.
  • Moderate changes. Some components aren’t suitable for the site supply, and some protective arrangements need changing to suit it. Motors, drives, transformers, power supplies, emergency stops and safety relays may need replacing or adding, with the wiring around them altered to match. Earthing, bonding and fault protection may need altering.
  • Extensive re-engineering. This is most likely with machines built for a different supply and standards, such as a US machine on a 60Hz supply. The control panel may be rebuilt, the wiring and components replaced, and the safety functions redesigned and validated to EN ISO 13849-1.

Several factors decide which level applies:

  • Supply voltage and frequency. UK mains is nominally 230V single-phase and 400V three-phase at 50Hz. A motor designed for 60Hz and run directly on 50Hz turns about a sixth slower, which can affect process speeds, fans and pumps. Transformers and power supplies rated only for 60Hz may overheat on 50Hz.
  • Component ratings and approvals. Parts built for another market may lack the ratings, approvals or markings needed to show compliance here.
  • Protective measures. Earthing, bonding and fault protection must suit the site supply.
  • Safety functions. Emergency stops, interlocks and stopping performance must meet EN 60204-1 and EN ISO 13849-1.
  • Documentation and labelling. Schematics and labelling must be accurate and usable in English.

Whilst the electrical work isn’t necessarily complex, it does need verifying, testing, and documenting. It’s a good idea to get an idea of the scope of electrical work before you import machinery, so you know which level to budget for.

Can older or second-hand machinery be CE or UKCA marked?

Imported second-hand machinery isn’t exempt. HSE says a second-hand machine not previously placed on the market or put into service in the UK falls under the machinery supply rules, so the person first placing it, who may be the importer or the user in a direct import, must carry out the conformity assessment. A used machine already supplied in the UK is different, but anyone supplying second-hand equipment for use at work must still ensure it is safe so far as is reasonably practicable. “Sold as seen” does not remove that duty.

Older machines already in service here must still meet PUWER. If you are buying a second-hand machine from another business, don’t use it unless it comes with physical evidence that its last required inspection was carried out. Machinery placed on the market before 20 January 2027 under the existing recognition provisions can continue to be made available in Great Britain, and the supplier’s existing obligations continue to apply.

What will it cost to bring imported machinery up to standard?

Imported machinery is often cheaper to buy, but the saving can shrink once it arrives. Budget for electrical re-engineering and replacement components, guarding, interlocks and emergency stops, and validation and testing of safety functions. Add translation of the technical file, declaration and instructions where they aren’t in English, and the technical file, declaration and marking if you are the manufacturer. Allow for downtime and delays while parts are sourced.

To avoid surprises, get a technical review and quotation for adaptation before you order, compare the landed cost including rework rather than the ex-works price, and put your requirements in the purchase contract, including UK supply, standards and English documents. Hold a contingency for what inspection uncovers.

How does SST support equipment operators importing machinery?

Before an imported machine goes into service, we check the evidence and close any gaps. That typically means:

Document review: We check the declaration against the nameplate, model and serial number. We confirm whether the machine carries CE or UKCA marking, and ask for the technical file or confirm that it exists.

Electrical assessment: We check the electrics against your site supply and EN 60204-1. Where they need adapting, we re-engineer them on site or in our workshop in Elland.

Safety function testing: We test stopping performance, emergency stops and interlocks. We assess safety-related control functions against EN ISO 13849-1.

Guarding review: We assess fixed and movable guards against EN ISO 14120:2015 and interlocking devices against EN ISO 14119:2025+A11:2026, including its requirements to minimise the possibility of defeat in a reasonably foreseeable manner. We check guard openings and distances to hazards against EN ISO 13857:2019. Where guarding falls short, we fit or upgrade it.

Conformity support: If the machine has no declaration, or you have become the manufacturer through a substantial modification, we support the conformity assessment, technical file, declaration and marking. See our CE and UKCA marking service.

PUWER installation inspection: Where the machine’s safety depends on how it is installed, we can arrange the PUWER installation inspection. See our PUWER services.

We also look for the faults such as a mismatched declaration, a missing file, non-English documents, and safety functions below the required performance level.

Request a paper copy of any digital instructions at order stage, so they are available when the machine is down or you have no internet access or access to digital records. Record your findings, including inspection results, in your machinery asset register.

Conclusion

Importing machinery works when responsibility is clear, the cost of adaptation is budgeted for, and the evidence is checked before installation. If you’d like a second pair of eyes on machinery you’re about to buy or install, we’re happy to help.

Frequently Asked Questions

Does the EU Machinery Regulation apply in Great Britain?

Not as EU law. SMSR 2008, as amended by SI 2026/867, continues to govern supply in Great Britain. From 20 January 2027 it lets you use the CE route by meeting the requirements of Regulation (EU) 2023/1230. The EU Regulation applies directly in Northern Ireland. Read our blog What Does the EU Machinery Regulation Mean for UK Machinery Owners? for further discussion of this.

Often at purchase, but you may need to budget for electrical re-engineering, guarding, testing, translation and documentation. Compare the cost after adaptation.

Frequently. Supply voltage, frequency, components and safety functions may need adapting, and the conformity evidence updated.

If it is imported and hasn’t been supplied in the UK before, the person who first places it on the market or puts it into service must carry out the conformity assessment, which can lead to marking. Older machines already in service here must still meet PUWER.

Yes. CE marking has been recognised in Great Britain indefinitely since 1 October 2024. From 20 January 2027, machinery that meets Regulation (EU) 2023/1230 and bears CE marking can also be placed on the GB market. UKCA marking is an alternative rather than a requirement.

Ask the supplier for it first. If none exists, you can’t lawfully put the machine into service until the conformity assessment is done and the declaration and marking are in place. If you’re the person first placing it on the market or putting it into service, that assessment may be your responsibility.

Picture of Allan Harris

Allan Harris

Allan Harris is a Director of Safety Systems Technology. With over two decades of industry experience, he is an expert in machine safety, machine guarding, and mechanical engineering. Since joining the company in 2009, he has specialised in product design, 3D modelling, and conducting risk assessments to ensure full compliance with PUWER and EN standards.